Kibali Gold Mine

DTP have been operating for more than 11 years at one of the biggest gold mines in Africa. To date we have moved more than 130 million BCMs of material, from eight different pits, stretching fifteen kilometres. 

KEY FIGURES 

 

  • More than 700 employees
  • 10 to 15 million BCMs per year
  • > 400 km of blast hole drilling a year
  • Turnover to date – USD 500 million

SCOPE OF WORKS 

 

  • Topsoil Stripping
  • Drill and Blast
  • Load & Haul
  • Dewatering
  • ROM Crusher Feed

EQUIPMENT

 

  • 10 Drill Rigs (Sandvik, Epiroc, Reichdrill)
  • 10 Excavators (Liebherr 9350, 9200 & CAT)
  • 34 Dump Trucks (CAT 777)
  • 12 Track Dozers (CAT D9)
  • 5 Wheel Loaders (CAT 992, 966)
  • 1 Wheel Dozer (CAT 834)
  • 4 raders (CAT 16M)
  • 2 Water Carts (CAT 773)

Location

Democratic Republic of the Congo, Central Africa

Duration

July 2012 – December 2027 (estimated end date)

client

Barrick / Anglogold Ashanti