Geita Gold Mine
Following on from the operation of the Morila goldmine and with the confidence of our Client, we worked on the Loulo gold mine, located not far from the Gounkoto site, from 2009 to 2012. This mine was a brownfield operation taking over from a previous contractor and doubling the production over a period of 1 year.
KEY FIGURES
- 1000 employees
- 23 million BCM per year
- Extraction of 90 million BCM
- 70% extraction with drill & blast
- 5 pits simultaneously
- Final depth 450m
- 131M USD TO contract
SCOPE OF WORKS
- Drill and Blast
- Load & Haul
EQUIPMENT
- 55 Trucks 92T
Location
Tanzania, East Africa
Duration
2002 – 2005
client
Anglogold Ashanti