
Morila Gold Mine
DTP operated the Morila goldmine between 2000 and 2009. This single pit operation produced 6.9 million onces of gold and is the first DTP’s operation in Mali.
KEY FIGURES
- More than 550 employees
- 9 million BCM per year
- Extraction of more than 80 million BCM
- 3 500 km drilled
- 190M USD TO contract
SCOPE OF WORKS
- Drill and Blast
- Load & Haul
EQUIPMENT
- 11 Drills / Atlas Copco DM 30
- 4 Excavators / Liebherr 9250
- 21 Trucks / CAT 777G
- 12 Trucks / CAT 769
- 6 scrapers / CAT 631D
Location
Republic of Mali, West Africa
Duration
January 2000 – April 2009
client
Anglogold Ashanti / Randgold Resources